Spring Construction Update
Colleagues,
As you can see, construction at the Mohegan
Campus is moving along rapidly, with both
the Shop Wing and the GYM/Cafeteria Wing
progressing a little ahead of schedule.
Here are some of the highlights and some of
the things we need to plan for:
·
Week of March 12th
- They will be saw-cutting flooring slabs in
the main boiler room to correct drainage
problems. This may be a little noisy, but
should not otherwise impact any of our
activities.
·
Spring Break – March 19th to
March 23rd
o
There will be asbestos abatement activities
in Rooms 202 and 210. These activities may
extend slightly into the main hallway, but
access to all other second floor offices and
classrooms will still be available.
o
On the third floor of the Classroom
Building, the contractors will remove all
ceiling tiles and grids in all classrooms
and offices in preparation for work this
summer. This will be somewhat unsightly
between Spring Break and the end of school,
but since this ceiling removal activity was
originally scheduled for last summer, we
have been fortunate to avoid this disruption
for most of the year. During these ceiling
removal activities, access to the third
floor will be limited to authorized staff
only.
·
March 26th to April 1st
– The Gallery will be closed for removal of
selected stained glass panels to take with
us to our new campus. Since it has not yet
been decided when the contractor will begin
limited demolition of the Gallery after that
date, we must assume at this time that the
Gallery will no longer be usable for College
activities. If this changes, we’ll let you
know.
·
Week of May 14th - May 18th
– As classes and activities are completed in
the Classroom Building, we will begin to
remove all furniture and equipment from all
spaces. Items removed will either be put
into temporary storage or moved directly to
new temporary office and classroom locations
in the Shop Wing or the GYM/Cafeteria Wing.
(Specific move locations will be available
to everyone shortly after Spring Break.) As
you will probably recall, there will be no
TRCC classes or activities in the Classroom
Building during the summer while classrooms
and labs on the second and third floor are
renovated. We will then return to these
renovated spaces in late August in time to
begin Fall Semester 2007. We will not
reoccupy the classes and offices on the
first floor. Instead we will use classrooms
in the Shop Wing to make up for the loss of
these spaces.
·
Approximately Mid-May
– At the present rate of construction,
temporary offices and work spaces in the
Shop Wing should be available to begin the
move of faculty and staff from the Annex.
(Packing boxes and instructions will be
provided to everyone by the beginning of May
to pack up their belongings to move to the
new spaces or to take home.) When these
moves are all complete, the Annex, Garage,
and Gallery will be turned over to the
contractor for demolition. With any luck,
this demolition, and the related dirt and
noise, will be completed before the start of
fall classes.
·
Early to mid-June
– Work on the GYM/Cafeteria Wing should be
completed by this time and moves will be
scheduled for Student Services and Cashier
staffs to move to temporary offices in that
wing at that time. These moves should all
be completed by July 1st so that
we can avoid as much disruption to
registration activities as possible.
Following the relocation of these staffs,
our existing student services offices will
be turned over to the contractor for
demolition and construction of their new
Administrative Wing.
·
Other Items of Interest:
o
Along with the completion of the Shop Wing
and the GYM/Cafeteria Wing, the site-work
and parking areas surrounding these new
buildings will also be completed, greatly
improving the appearance of the area. This
will also provide parking that will be more
readily accessible to these new buildings
most of which will be designated as faculty
and staff parking. At the same time however,
existing faculty and staff parking will be
closed and used as the construction
“lay-down” area for the new administrative
wing. The net number of dedicated staff
parking spaces will remain about the same,
but the spaces will be spread around the
perimeter of the new buildings rather than
gathered together in the same location.
o
In response to frequent questions on these
subjects, we will have access to the
Auditorium, the Library, the modular
Classrooms, the Bookstore, the main IT and
Communications Closets, and the Registrar
Files Storeroom on the 2nd Floor
throughout our remaining time on the Mohegan
Campus. The Cafeteria on the Mohegan Campus
will be closed right after graduation and
will reopen in a different location in the
new GYM/Cafeteria Wing when the fall
semester begins.
On the Thames Valley Campus,
progress is a little less visible, but
moving forward nevertheless. The final
building permit from the State Fire Marshall
has been held pending issues with the State
Traffic Commission and the State Department
of Environmental Protection. It appears
however, that these issues will be resolved
shortly and construction can begin near the
end of this month. In the meantime, we are
completing plans for our portion of the
renovations in the North Wing and should be
starting work shortly. Our general
contractor and construction administrator
have also been using their time productively
reviewing and clarifying specifications,
preparing submittals, and finalizing details
with subcontractors. This should permit
construction to jump off to a fast start
once the go-ahead from DPW is received.
My special thanks
to everyone for your continuing support and
patience with the many annoyances and
inconveniences caused by the project. Your
good natured responses to the day-to-day
frustrations facing all of us and our
students have been a tremendous help and a
major factor in minimizing problems
throughout the college. Things are going to
get even busier as we approach graduation,
so please keep up the good work and don’t
hesitate to call if you have any questions
or suggestions.