College Parking / Construction Updates

 

       

Recent developments  

Monday December 18, 2006: PRE-HOLIDAY CONSTRUCTION UPDATE

CONGRATULATIONS TO US ALL!!

Our TRCC Construction Project is finally officially on its way.  On Friday, December 8th, the State Bonding Commission approved $76,149,198 for the project and Governor Rell praised this action as a wonderful investment for the State.   All the final paperwork for approval and award of the project by the Commissioner of Public Works and the State Attorney General is now in process and will hopefully be completed by January 15th.  In anticipation of this approval, we held our first pre-construction meeting today with all the key players. Our General Contractor for the project, O&G Industries, said they were really looking forward to working with the college and were prepared to start work within days after the State authorized them to begin.

ASBESTOS ABATEMENT:

Other work at the Thames Campus is already beginning today in some areas as our asbestos contractor prepares to initiate abatement activities throughout both floors of the north wing of that campus.  For the next couple of days, all furniture and other equipment will be removed from these spaces and actual abatement should begin later this week.  Abatement will be completed on the lower floor by not later that January 15th and on the upper floor by the end of January. Immediately following this abatement, renovation work on the North Wing will commence by the General Contractor with the intention to complete that phase of work and have these spaces ready for classes in September 2007.

WORK AT THE MOHEGAN CAMPUS:

Construction of the Norwich Technical High School project at the Mohegan Campus is moving along right on schedule.  As you can see, the Shop Wing is rapidly becoming enclosed, and the Gymnasium/Cafeteria wing is beginning to take shape.  Locations for temporary offices for faculty and staff starting next summer are being finalized and should be available for review by everyone at the start of the spring semester.  We have just switched over from our old well water to city water starting this week so a slight difference in taste may be noted.

COLLEGE CLOSURE ON DECEMBER 29th:

On Friday, December 29th, the college will be closed to permit a major power cutover at the Mohegan Campus which will leave that campus without power for most of the day.  At the same time, our asbestos contractor at the Thames Valley Campus needs to abate the center corridor by the elevator, library and cafeteria leaving that campus with no handicapped accessibility and without proper emergency egress from many areas.  Because of these ongoing projects, the Chancellor has approved a total closure of college facilities on that date with the exception of selected maintenance staff who will need to be present to support and monitor these projects.

--Joseph Anderson Jr., Dean of Administration, (860) 823-5202

Get Acrobat Reader

Campus Consolidation web

Construction update from November 3, 2006
Construction update from September 28, 2006
Construction update from September 25, 2006
Construction update from August 16, 2006
Construction update from July 20, 2006
Construction update from June 28, 2006

This website is published and maintained by Three Rivers Community College.
Last revision 12/19/2006. 
To respond with feedback or questions about the website contact the web maintainer.

 

 

©2004 Three Rivers Community College
Directions | Contact the Webmaster| Text only site